Export Operations
An export request starts with a quotation request, takes shape through supplier selection and is completed with the customs declaration.
Quality performance comes before price
For an MV switchgear or LV panel order, manufacturer capacity and delivery schedule are checked first; past quality performance is weighed alongside technical suitability.
Once production is complete, a factory acceptance test (FAT) is requested and the results are checked before shipment. Packaging differs depending on sea or land transport; silica gel is added for moisture-sensitive equipment.
What's Included
- Supplier selection and quotation comparison
- Factory acceptance test (FAT) tracking
- Packaging suited to the shipping method
- Certificate of origin and ATR document preparation
- Customs declaration and commercial invoice
- Shipping organization
Standards We Apply
ATR
Movement certificate (EU Customs Union)
Equipment that doesn't pass the factory acceptance test is considered never to have reached the site.
Frequently Asked Questions
Is a factory acceptance test mandatory?
It isn't mandatory, but we recommend requesting a FAT before shipment, especially for custom-built equipment, since it catches defects before they reach the site.
Which documents are prepared as standard?
A commercial invoice, certificate of origin and, where needed, an ATR movement certificate are prepared as standard; additional documents may be requested depending on the destination country.
What determines the shipping time?
It depends on the production schedule, the shipping method and how quickly customs procedures move.
Do you also handle small-volume equipment orders?
Yes, we handle everything from single-item part orders to multi-item project shipments.
Request a Quote for This Service
Give us a brief outline of your project and our team will get in touch.